Three figure numbers represent lode numbers.
Part of an explosives box found in 2018 in Lode 702
Photo: George Harvey
The following are just a few chapters from the book: 'The Milwr Tunnel
- Second Edition' (see "Cris's Shop Window" on left for details), with
one or two small additions.......
Tunnel Progress before the formation of HDUM
The Milwr Tunnel was begun in July 1897 from a point 9 feet below high
water mark at Boot End near Bagillt (SJ 213760) by the Holywell-Halkyn
Mining and Tunnel Company. A self-acting flood door was installed to
prevent inundation by the sea at high tide: A high tide pushed the door
closed causing tunnel water to be diverted into channels and lagoons
along the salt marsh. Mining of the tunnel began south-westwards towards
Herward Shaft (SJ 196740). At the same time an intermediate shaft was
sunk (SJ 204749) from where two headings were driven, one towards
Herward Shaft and the other to meet the crew driving from the portal.
Thus the tunnel was being driven from three different points
simultaneously. When both drivings met, the centres of each were only
one inch out of true, a tribute to Mr N.R. Griffith of Wrexham, the
Engineer.
The tunnel gradient is 1:1000 throughout. It is initially circular in
section, 8 feet in diameter with a channel for water in the floor 1 foot
6 inches deep by 6 feet wide. Rails were laid on timbers above the water
channel. The tunnel walls are brick lined for 1.5 miles where the tunnel
passes through shale and coal measures, but thereafter is in chert or
limestone and is generally self-supporting. 307 yards north-east of
Herward Shaft, a branch tunnel known as the North Cross was driven
north-west to intersect the Beili Gwyn and Old Milwr Veins. The tunnel
south from this area changes to a square section of 8 feet x 8 feet.
From Herward Shaft the tunnel passes through Milwr Mine for a short
distance to Caeau Shaft on Caeau Mine (SJ 195729) where driving stopped
2 miles from the portal in 1908 at the limit of the company’s mineral
boundary. The tunnel, at this time, drained an average of 1.7 million
gallons per day (gpd) or 8,000 tonnes. The fastest rate of tunnelling
was 54 feet a week. The veins cut by this section of tunnel are, from
north to south Pen-yr-Hwylfa, Dolphin, Drill, Coronation and Pant-y-Pydew
or Caeau Vein. The Old Hwylfa Vein was drained by a higher level
cross-cut driven from Milwr Mine as this lode could not be traced at
tunnel level.
NB The text
on the photo is incorrect: The view is actually looking east along the
Pantymwyn Vein
(Lode 547) midway between the Milwr Tunnel and Cae Mawr Shaft.
With thanks to Nick Carter for the information
In
1913 an Act of Parliament allowed the company to continue driving the
tunnel which reached this extended mineral boundary in 1919 at the
hamlet of Windmill on Halkyn Mountain. The Act enabled the company to
mine without legal challenges from land or mineral owners, whose
property the tunnel passed through. Rates of advance of 40 to 45 feet a
week were achieved during the early years of the First World War. A two
shift system was operated; one drilling, the other for shooting
(blasting) and ‘mucking out’: The drilling team consisted of
three drillers and one ‘spanner-man' working on the face together. Each
charge or blast gained an advance of 4 feet. The average cost per foot
was £2-6-8d compared with £4-2-6d a foot spent driving the northern
brick lined section. During this southerly advance, the Erw Vein was cut
where water of about 1,400 gpm entered from natural fissures. Grainger's
Vein, the Pant Lode and what may have been the Old Chwarel Las Vein were
also intersected. Upon reaching the company’s boundary in 1919 Caeau
Shaft was sealed off and all work on the tunnel was again halted. At the
intersection of the Pant Lode, a flooded cavern, known locally as a loch
or vugh, was cut at 6am on 5th January 1917. This caused St Winefride’s
Well at Holywell, 2.5 miles to the north, to run dry 11 hours later. The
burst of water swept loaded trucks along the tunnel until they jammed
and sand blocked the tunnel, being 2 feet deep at the entrance,
seriously hampering progress for many weeks. Water levels in a number
of neighbouring mines were also affected.
The water issuing from this vugh eventually decreased from 10,000 gpm to
a steady flow of 4,000 gpm from feeders on the east and west of the
tunnel. Interestingly, the water temperature of the east feeder was
about 49 °F, whilst that from the west was 56 °F, suggesting the warmer
feeder passes through a deep-seated aquifer. As the water at St.
Winefride’s Well was an important source for local industry at the time,
pumps were installed at depth in Roskell's Shaft at Holywell (SJ 180765)
as an alternative supply. Roskell’s Shaft adjoins the Holywell Boat
Level whose
portal (SJ 184764) lies near St. Winefride’s Well.
Halkyn District United Mines
Following a takeover in 1928 by the Halkyn District United Mines Ltd (HDUM),
Caeau Shaft was re-opened and the 5,000 feet to the tunnel face at
Windmill was reconditioned to cope with the large volume of water now
flooding the rails. The tunnel floor was sectioned off and one side
filled with debris from the face upon which the rails were laid 3 feet
above the original floor. As this reduced the walking height of the
tunnel, ten pit ponies of not more than 12 hands were purchased, three
to work each shift of eight hours with one in reserve. A pony hauled 3
or 4 trains each shift of 5 wagons weighing 5.75 tons per train, the
slight gradient making the task less onerous.
The tunnel now rapidly pushed south beneath the hamlet of Catch reaching
Pen-y-Bryn Shaft (SJ 202707) in July 1929. Surface operations were
transferred to Pen-y-Bryn the following month. This shaft measured 9
feet by 7 feet by 800 feet deep. It was fitted with two cages in balance
each holding 8 men or one loaded mine wagon or tub. The cages were
hoisted by an 80 horse power electric motor through double gearings onto
double cable drums 5 feet in diameter. Shaft signalling was controlled
by two men: the banksman on the surface and the onsetter at shaft
bottom.
Driving south from Pen-y-Bryn Shaft the tunnel was then driven larger in
section being 10 feet wide and 8 feet high. A water channel, known by an
American mining term as “the grip”, was cut to one side of the
tunnel 4 feet wide and 2 feet deep. A major branch tunnel was driven
east from a point three quarters of a mile south of Pen-y-Bryn. This was
driven for one mile to Rhosesmor where lodes 674 (Barclay’s) and 675
(Powell’s) yielded major deposits and were worked successfully for many
years. Three quarters of a mile south of this branch tunnel, the main
tunnel intersected lode 656. This previously unknown vein was the first
to provide healthy profits for the faithful shareholders of Halkyn
District United Mines. As the tunnel progressed southwards towards
Hendre, an old shaft now known as Olwyn Goch (SJ 201677) was enlarged to
12 feet by 12 feet 6 inches and deepened to 470 feet. During this work
it was found that the original shaft was not vertical and was 8 feet out
of true at its bottom. The tunnel reached Olwyn Goch in 1931 and in 1934
surface operations were transferred from Pen-y-Bryn to Hendre.
Rare photo showing the original livery of loco 2498
Taken from Bagnall's catalogue and kindly supplied by
narrow gauge historian Vic Bradley
Ruston Hornsby loco RH 183727, photographed by P.
Hindley in 1967. Kindly supplied by Vic Bradley
Olwyn Goch Shaft had a similar hoist to that of Pen-y-Bryn but had
larger cages, each carrying 16 men or 2 mine wagons. At this time Olwyn
Goch was chiefly used for raising men and materials, until the 1940s
when limestone quarried underground was raised here. At the same time
Pen-y-Bryn Shaft was being used for winding ore and materials. The speed
of winding at both shafts was 710 feet per minute or 8 miles an hour. At
the surface close to Olwyn Goch Shaft were the offices, changing rooms,
bath houses and lamp rooms sufficient for 500 men. The shaft top was
situated on the hillside above the buildings, therefore a passage was
driven into the shaft from a point immediately behind these buildings
for easier access. Fixed ladders, supported by platforms in the side of
the shaft, also provided an alternative route to surface for the men in
an emergency. By
1938 the tunnel had reached lode 547 (Pant-y-Mwyn vein) when low ore
prices once again halted progress. All but 40 of the 650 men were made
redundant and an era of great productivity drew to a close. With work on
the tunnel at a standstill, a little prospecting was being done during
1938. The continuation of lode 630 was sought beyond a cross-course
(fault) and found by a team led by the new foreman, John Bellis. In
1939, Pilkington’s of St. Helens became interested in the high grade
limestone of the mine for glass making and work began excavating large
quantities of the stone, chiefly from the area to the west of Olwyn Goch
Shaft, near the hamlet of Hendre. This limestone was also used for
agriculture and as an ingredient in toothpaste. Ore
was shipped away for smelting as all the local coastal smelters had
closed before the 1930s. Ore was shipped to Avonmouth or Chester. The
Chester smelters 'Associated Lead Manufacturers Ltd' handled Halkyn's
ore in the later period.
Small enamel sign
Excepting during the war years, when lead mining would have taken
priority over limestone, this underground quarrying continued until
1969 and resulted in a series of impressive chambers, some up to 80
feet high which, if joined end to end, would extend for 2 miles.
Limestone output was 70,000 to 80,000 tons per annum. A jump in ore
prices in 1948 prompted renewed activity at the main tunnel face and
after a 10 year stoppage, it advanced south beneath the Hand Inn at
Gwernaffield. A new lode, 538, was cut here, but contained very little
ore. Further south however, lode 530 was discovered, which was rich in
ore and provided work for 10 more years. Mid-way between Gwernaffield
and Cadole during the 1950s, the tunnel struck lode 524 (Pant-y-Buarth
Vein), followed by lode 501, both rich veins which were worked until
the tunnel reached its present end in 1957 at lode 477 (Cathole Vein)
just yards before the Mold-Ruthin road. Lode 477 was unproductive at
this point but a feeder brought in large volumes of sand and clay with
water from natural cavities above. Miner Walter Block of Mold stated
that “enormous quantities of sand were washed down the tunnel
amounting to thousands of tons and tubes of clay were being forced
under great pressure into the tunnel”. No lead was mined from 1958 to
1964 when work centred on the limestone mining at Hendre. A final jump
in ore prices in 1964 kept the few men busy until 1977 removing ore
from the existing lodes when the workforce never exceeded 40.
Thereafter work revolved around maintenance and tunnel repairs until
final closure in 1987. The
lead mines of Flintshire, since records were first kept in 1845 up to
the first world war, produced a total of 400,000 tons of lead ore and
over 100,000 tons of zinc ore. Since then, the Milwr Tunnel and
associated lodes have produced a further 200,000 tons of lead ore and
around 80,000 tons of zinc ore, the majority of this being extracted
prior to 1957.
Empty waggons at Olwyn Goch Shaft 1976
From the collections
of the National Monuments Record of Wales: © Christopher J. Williams
© Crown copyright: Royal
Commission on the Ancient and Historical Monuments of Wales
© Hawlfraint y Goron: Comisiwn Brenhinol Henebion Cymru
Simple seating and stove in a corner of Olwyn Goch winding house in 1978
Men ready to descend Olwyn Goch Shaft 1976
From the collections
of the National Monuments Record of Wales: © Christopher J. Williams
© Crown copyright: Royal
Commission on the Ancient and Historical Monuments of Wales
© Hawlfraint y Goron: Comisiwn Brenhinol Henebion Cymru
Olwyn Goch shaft bottom in 1978, shortly after the shaft signalling
system had been modernised
Miners beside an Eimco digger in the drift off the Milwr Tunnel leading
to Cae Mawr Shaft (at Gwernaffield)
From the collections
of the National Monuments Record of Wales: © Christopher J. Williams
© Crown copyright: Royal
Commission on the Ancient and Historical Monuments of Wales
© Hawlfraint y Goron: Comisiwn Brenhinol Henebion Cymru
The last mining for galena, on Lode 524 (Pant-y-Buarth) in
1976 Photo: Chris Williams
The Mill at Olwyn Goch
By
the mid-1930s Olwyn Goch had taken over from Pen-y-Bryn as the centre of
operations. It was equipped with an elaborate milling complex to process
raw material and all the necessary infrastructure to ensure maximum
working efficiency. A First-aid room and First-aid lecture room were
provided as well as separate heated changing rooms for management and
miners. The Underground Manager was provided with his own office,
bathroom and lavatory. Cycle and motor-cycle sheds were also provided.
The site had a canteen, workshop, carpenter’s shop, blacksmith’s shop, a
mechanical department office, electrician’s shop, rip bit shop, stores
and survey office. The survey and drawing office contained the company’s
large collection of old mine plans. A fully equipped laboratory
regularly sampled and monitored ore quality and geological specimens.
The site was linked to the Mold-Denbigh railway line by sidings and a
weighbridge was built for road haulage. A man arriving for work would
change, collect his charged lamp and place an individual numbered brass
tally to indicate their presence underground. He would then walk along
the short tunnel leading to Olwyn Goch shaft to be lowered by cage into
the mine.
On
very icy mornings at the main shaft, it was common practice to lower and
raise the empty shaft cages several times to remove any dangerous
icicles hanging in the shaft. Despite this precaution, the first men
down had to endure “the disturbing sound of
crunching and cracking” during the descent. In 1975, a major
rock fall seriously damaged the ladderway in the shaft and most of the
ladders and platforms were replaced with best quality timber. The oak
ladders are in remarkably good condition today.
The sign above was found in a poor state and is shown in
its restored condition
The Workforce
The great majority of the workforce were new to metal mining and had to
be trained. A mine survey in 1934 showed that of 600 men, only 17 had
previously worked in lead mines of the area and of these, only 12 were
fit for underground work. The turnover of miners was quite high and
during the late 1930s many of the workforce came from the slate quarries
of Snowdonia such as Maenofferen, Penrhyn, Llanberis and Trecastell.
Others came from local collieries at Bagillt, Buckley and Nerquis (Nercwys).
Employment records show that many of these men were aged over 60, some
of whom continued working underground to the age of 70.
Although some men were ex-colliers, conditions in the lead mining
industry were so different that it was considered that "a
coal miner in a metal mine was sometimes a menace". Training
was therefore essential and continuous and meant that some working
methods had to be simplified. In general one man learnt one job. Shift
foremen were usually promoted from the ranks. Miners were issued with a
small book of rules outlining rates of pay and requirements of the job.
Attempts were made to employ graduate foremen but this was unsuccessful.
Each group of lodes known as a ‘mine section’ had a Section Manager or
Mine Captain who, in turn, was responsible to the Mine Manager.
A
shift system was operated from midnight on Sunday to Saturday afternoon.
This gave men the opportunity to work 17 shifts in three weeks. It also
ensured that mining was continuous for 138 hours a week. The average
wage in 1936 was £3-12-6d a week payable each alternate Friday. Should a
safety man be unlucky enough to have an accident occur in his section,
he would be deducted 2s-6d for each absence of three or more shifts.
Surface mill workers at Pen-yBryn would average £2-12-0d a week which
included an efficiency bonus. Wages accounted for two thirds of the
company's total expenditure.
Glynn Morris, photographer, once worked for HDUM. Responsible for
drilling machines and drill bits, he was known as a ‘steel nipper’. Mr
Morris described an incident when a miner alone in the Halkyn Lode
suffered a lighting failure. “He was lost for
three days”. Since that time company policy dictated that men
should work in no less than pairs. Mr Morris also described the
operation of raising loaded wagons at Pen-y-Bryn Shaft: “The
underground passing place for locos was called ‘The Shunt’. The
onsetter’s job (underground) was to push loaded wagons into the cage
which would push out the empty tub on the opposite side. The banksman
(surface) would push out the loaded wagon which ran down a slope to ‘The
Creeper’. This was a chain hauling device which pulled the tubs up a
slope to the tippler, where ore was tipped onto the jigs. When 40 or 50
empty wagons were ready (had been lowered underground), the loco took
them away”.
The highly profitable Powell’s Lode was named after Captain Edward
Powell, whose mining family had moved from Dylife in mid-Wales. The
title ‘Captain’ was commonly applied to the respected post of mine
manager. His gravestone can be seen today at Halkyn Church. Captain
Powell’s son Joseph had a daughter who Glynn Morris married.
The men were generally well cared for but a strike in 1934 resulted from
moving the centre of operations from Pen-y-Bryn shaft at Halkyn to Olwyn
Goch shaft at Hendre, some two miles to the south. The Manager at the
time, Mr J. B. Richardson told the men "You can
stay out as long as you like, I have bread forever". When the
men eventually returned to work, it was for one shilling a day less than
before the strike. Despite this disagreement, the mine was regarded by
the men as a happy place in which to work.
Modern Exploration
After closure a water company acquired water extraction rights to the
mine complex. This company now supplies industry on Deeside from the
flow issuing at the portal in Bagillt. In 1995 mine enthusiasts from a
local club negotiated an access agreement. They then began a programme
of exploration which at the time of writing, has resulted in over 26
miles of workings being examined.
Initially, exploration centred upon the lodes at Milwr Tunnel level.
These workings are distinctive in that all ore and accompanying minerals
were entirely removed from the lodes for separation on the surface. This
resulted in large open stopes, typically 2 or 3 metres wide and
frequently over 65 metres in height, being perhaps half a mile in
length. Lodes were extracted upwards in this manner until the ‘old
man's’ workings were encountered above or until the ore pinched out.
In the older workings, only ore and perhaps a minimal amount of waste
rock was removed, resulting in smaller passages but more interesting
workings. As a general rule, the higher the workings above Milwr Tunnel
level, the older they are; workings closest to the surface possibly date
back to Roman times.
It
soon became obvious that 1930s rotting ladders could not be relied upon
to reach the higher workings. A method was therefore evolved requiring a
5 metre aluminium ladder and a battery-powered drill. After climbing the
ladder, a bolt with ladder-bracket could be fixed to the stope wall.
Suspended in his sit harness at the top of the ladder, the operator
could then raise the ladder and clamp it onto the bracket in order to
gain another 5 metres and so on. Having reached old workings above,
permanent rigging would then be installed for future trips.
Due to the length of exploration trips being carried out, alternative
entrance points became necessary. Permission was sought and two old
shafts were re-opened to act as emergency exits. These shafts also
provided sporting through-trips; one being a 500ft deep shaft at
Pantymwyn, the other a 650ft deep shaft at Halkyn. Both shafts were
rigged for rope descents and ascents.
A
new telephone line was laid the two miles from Olwyn Goch Shaft to
Powell’s Lode Cavern and the club installed several underground
emergency stores with ration packs and first aid equipment.
After more than twelve years work in the complex, several areas of
higher workings have been made accessible and numerous round-trips can
now be undertaken. Grosvenor Caving Club consequently arrange regular
trips for visiting clubs from throughout the UK, in which over a hundred
suitably experienced groups have so far taken part.
Further work has been carried out to repair nearly three miles of rail
track. The original locos were in a poor condition, therefore a new
diesel loco in kit form was built by club members and lowered down the
entrance shaft. It was assembled below ground and now carries visitors
to the cavernous limestone workings below Hendre or to Powell’s Lode
Cavern beneath Rhosesmor.
View across the 'bottomless' lake in Powell's Lode
Cavern Photo by Paul Deakin
Powell's Lode
Cavern beneath Rhosesmor
Photo by Paul Deakin
Access along the main tunnel can be ‘dry walking’ during the summer
months, but in wetter weather the grip overflows covering the rails
and making walking almost impossible over long distances. In contrast
however, most of the lodes are dry and dusty places, involving no more
than ambling along roomy open stopes, or perhaps stepping over piles
of dry rotting timbers which have fallen from high overhead. Most of
these lodes still exhibit timber ladder-ways and ore chutes together
with the occasional abandoned mine wagon. The older workings above
contain artefacts such as hand winches, bell-signalling devices, a
wooden candle box, a compressed air winch, a wall-mounted carbide
lamp, etc.
One of the more interesting areas is accessed from a point half way down
Olwyn Goch Shaft: Stepping out of the shaft into old workings, a branch
of the nearby Halkyn Tunnel is entered. This was driven specifically to
drain the old pre-1880s workings just north of the hamlet of Hendre.
These workings, due both to their age and the fact that they are ‘flat’
(near horizontal) workings and not vertical veins, are entirely
different in character to those already mentioned. Most of this area can
be seen on a four hour round-trip passing two interesting old drum
winches, one of which was operated by compressed air. Underground
stables once existed nearby, but these have now been lost due to surface
quarrying.
Much of the five mile long Halkyn Tunnel can be visited, but this
involves longer trips typically taking 10 hours or so. The route from
Olwyn Goch at Hendre involves walking north (if the train has departed)
for a mile along the main tunnel, then following a branch tunnel east
for another mile. Prussiking is then required to ascend 55m through old
workings above Powell's Lode, from where a further four mile round-trip
begins and ends. The journey passes through Rhosesmor Mine, the Halkyn
Tunnel and East Halkyn Mine. Items to note en-route include a passage
wall where old miners signed their names, two sets of electric pumps
installed in 1907 and 1908 (used to drain the mine in the days before
the Milwr Tunnel had reached this area), old timber wagons abandoned a
century earlier and a wooden peg counting board for recording up to one
hundred loads, situated at the top of a steep incline. Here an operator
once spent his shifts lowering wagons loaded with ore down to the Halkyn
Tunnel below.
The drill carriage above was
originally fitted with four flanged wheels to enable it to be moved on
rails. Once
in place, the wheels would be removed and the main threaded shaft would
be tightened between floor and ceiling to fix the device firmly in
place. Drilling machines were then attached to the mountings shown. The
drilling rigs of the 1930s were far lighter and easier to move.
Artefacts & Papers
Although it was general policy to remove equipment from exhausted lodes,
a surprising amount still remains scattered throughout the workings
today. The loco track from Pen y Bryn to within half a mile of Cathole
Lode and along the Rhosesmor Branch is completely intact totalling over
6 miles. At Olwyn Goch Shaft in the main tunnel lie two diesel locos, a
loaded train of about a dozen wagons, a double bogey rail transporter
and a diesel truck for fuelling the locos. The compressor chamber in
this area was turned into a workshop in later years and although most
equipment was removed, much in the way of spanners, jack-hammers,
work-benches and fittings still remain, although dry-rot has now
destroyed most of the timber benches. The charging bay beside the
workshop is almost complete and exhibits batteries connected ready for
charging.
Junction of the Rhosesmor Branch Tunnel with the main
Milwr Tunnel
The water channel takes water from a natural cave
system that supplies the lake in Powell's Lode
Photo by Paul Deakin
At Pen-y-Bryn Shaft lie two man-riders and a covered truck used for
the conveyance of the mine manager specially built for the purpose.
The limestone workings west of Olwyn Goch also contain up to 40 mine
wagons together with several Eimco rocker shovels. Not to be
overlooked are the areas used by miners for discarding rubbish. At
such places can be found old boots, cigarette packs, old tins and
newspapers dating back to the 1930's. The onsetters cabin at Olwyn
Goch Shaft has oilskins hanging on a hook on the wall, but the table
was consumed by fungal growth within a few years of the mines closure
in 1987.
"The Quarry", an area covering several acres of such chambers mined
for high quality limestone.
Photo by Paul Deakin
Little remains on the surface as all headframes have now gone and all
shafts connecting with the tunnel have been sealed off. At Olwyn Goch
Shaft a few office buildings and a milling shed remain, but their
contents were removed prior to closure. The winding shed at Cae Mawr
Shaft near Gwernaffield still exists. This housed two winding drums
with cables, but they were dismantled for scrap early in 1993.
Mining enthusiasts hoped prior to closure, that a show-mine could have
been developed at Olwyn Goch Shaft utilising the original 1930's
equipment, but apparently none of the bodies consulted could be
persuaded to act. Club members have saved or restored numerous
threatened artefacts. These remain in private hands awaiting the
creation of an appropriate local museum.
Before closure Halkyn District United Mines Ltd deposited their
collection of mine plans with the Mines Records Office. These are now
available for public viewing at the County Record Office, Hawarden (Ref:
D/HM). A Record Office catalogue entitled ‘Holywell-Halkyn Mining &
Tunnel Co Plans’ lists the 354 mine plans and maps available. These not
only cover Flintshire mines, but also some in Denbighshire and a few in
Cardiganshire, Caernarfonshire and Shropshire.
Club members have also managed to obtain a considerable number of
documents relating to Halkyn Mines. These include blueprints and
drawings of many items of equipment together with 1930s and 1940s
manufacturers’ equipment catalogues, employment records and many
‘Standard Drawings’. Further documents include company inventories for
1936, 1938 and 1941. These describe every single item owned by the
company from derelict engine houses to tea-cloths. They provide a
detailed insight into day-to-day workings of the mine.
A
database of the saved documents and of (some of) the artefacts
found in the workings is held by the club (and can be downloaded from
this site at the "Assorted Information" page). The 1941 inventory is
currently on loan to Flintshire Record Office, Hawarden.
Artifacts continue to be re-discovered: In December 2007 Grosvenor
Caving Club entered a remote area some 40 metres above the level of the
Halkyn Tunnel in the eastern end of Great Halkyn Lode (East Halkyn
Mine). Here miners had abandoned all their equipment. Amongst the items
found were various drilling machines, drill steels, glass bottle, clay
tobacco pipe, various tools, rails and wagon, safety fuse with crimping
pliers, shovel, tin box, metal water bottle, compressed-air windlass and
an air pressure gauge. A date of 1898 was found on a passage wall nearby
with the name of miner 'B. Hough'.
Where did the headframe go?
Explorer Access
When the mine was still operating in the 1980s, a few explorers began
to examine the mine from Hendre Quarry, which had cut into the old
workings of North Hendre Mine, but this old entrance has now been
quarried away. The entrance led downwards and eastwards to a long
cross-cut which, in turn, led to Olwyn Goch Shaft at a point about 200
feet below the surface. After the mine closed in 1987, explorers,
faced with the prospect of no access whatsoever, began talks with the
owners and an agreement was eventually signed. This was subject to
several of the owners conditions including the setting up of a leader
system and of course, public liability cover for all visitors. This
system has operated well on this basis since 1995 as a result of the
efforts of Grosvenor Caving Club.
____________________________________________________________________________________________
Clwyd Powys Archaeological Trust describe the mine thus:
Halkyn District United
CPAT Historic Environment Record number 18015, grid reference
SJ20307070.
Workings
In 1928, the Halkyn District United Mines Ltd began to extend the
sea-level tunnel. The Company was the amalgamation of nine old mining
companies and two drainage companies. The sett worked eight main veins
off the sea-level tunnel and covered an area of 25sq miles, from
Windmill to the south of Eryrys. The main shaft and mine area remains
in the Wimpey Asphalt Pant Quarry. Referred to as the New North Halkyn
Mine and the Pen-y-bryn Shaft, it was sunk to 800ft to raise ore and
acted as the main shaft on the Holywell-Halkyn Drainage Tunnel
(previously known as the Deep Level Tunnel). The Pen-y-bryn Shaft was
an upcast shaft for the ventilation system. A shaft to the south of
the main shaft was located at SJ20257055. To the north-east of the
main shaft, a shaft was located at SJ20367083.
NB
The misleading description above seems somewhat
at odds with what is known of this major mine company. Furthermore,
the main shaft on the Deep Level (or Halkyn) Tunnel was Lewis's
Shaft at Halkyn and not Pen-y-bryn as stated. A large milling complex
existed at Lewis's Shaft prior to the driving of the Milwr tunnel
through the area and a passage was driven north-west in search
of ore from Lewis's to Pen-y-Bryn in 1905-6 (at a depth in Pen-y-bryn
of 609 feet), but little ore was found.
The Holywell-Halkyn Drainage Tunnel was
also known as the Milwr Tunnel or the Sea-Level Tunnel.
It was driven from sea-level at Bagillt for 10 miles to Cadole.
The Deep Level Tunnel (named after the
Deep level Lode at Halkyn) was also known as the Halkyn Tunnel,
the Old Drainage Tunnel or the 1875 Tunnel. It was
driven from 180 feet above sea level from near the town of Fflint for
5 miles to Pantymwyn.
Clwyd Powys Archaeological Trust carried out a
'Clwyd Metal Mines Survey' and have an index of mines on-line at:
http://www.cpat.org.uk/projects/longer/mines/mines.htm
Some entries such as that above contain
significant factual errors and show a limited understanding of the
underground workings and arrangement of veins. Researchers should
therefore treat entries with a degree of caution.